Wilmington Harbor Inner Ocean Bar Project 2022/2023

The U.S. Army Corps of Engineers, Wilmington District has contracted with Marinex Construction to provide maintenance dredging of the Federal navigation channel.  The dredging will be accomplished with a hydraulic cutter suction dredge.  Approximately 1,000,000 cubic yards of the dredged material will be placed on South Beach on Bald Head Island.  NOTE: The photo above was taken in January 2021.

CONTRACTOR: Marinex Construction

DREDGE: Savannah – Cutter suction dredge

CONSTRUCTION START DATE: December 10, 2022*

APPROXIMATE END DATE: April 3, 2023*

MATERIAL AMOUNT: Approximately 1,000,000 cubic yards
(Total was estimated to be 1,134,000)

*Start and end dates are rough estimates since weather and mechanical impacts can change the project schedule.

Savannah Dredge (photo from Marinex Construction)

PLACEMENT: South Beach, Bald Head Island – starting on the west end near Sandpiper Trail and approximately ending near Killegray Ridge.

WHAT TO EXPECT: The beach will remain open except for the areas of immediate construction where a 1,000-foot section of the beach will be closed at any given time when nourishment is underway. Due to the many variables associated with the construction progress, such as mechanical or weather impacts, it is extremely difficult to forecast when the contractor will have a particular section of the beach closed. There will be a large pipe that carries the sand slurry down the beach and heavy excavation equipment which will be working 24/7 until the project is completed. There will be noise from the large machinery 24/7, this will include the “back-up signals” from the machines and lighting which are required for the safety of the crew. Sand ramps will be spaced along the beach (approximately every 400 feet) to allow beachgoers to walk over the pipe and access the ocean.

Please help the construction crew by being mindful of the construction fencing and signage. Do not go beyond any signage or barriers as doing so may place yourself and others in harm’s way.

INQUIRIES: Can go to public.information@villagebhi.org or (910) 457-9700 ext. 1025 (view FAQs at the bottom of this page).

MAPS: For the Army Corps of Engineers progress map click HERE.

The map below shows the approximate location for the starting point and ending points for sand disposal on South Beach, the beach accesses, the location of construction, and photos will be added as the construction site moves down South Beach.

View on Google Maps

Updates:

April 6, 2023 – Marinex is working right now to get all of the submerged pipeline removed. That will take a day or two more and then they will proceed with removing the equipment from the BHI shoreline. It will take a couple of weeks for them to move everything off the shoreline.  They will be using escorts when moving all equipment to ensure public safety.  

March 25, 2023 – From the ground, it looked like they were packing it up, but they have approximately 2-3 days of dredging left. Unfortunately, they will have unsafe working conditions most of the weekend. Marinex is monitoring the weather forecast and planning on resuming operations Sunday or Monday which will put them at finishing the project around the middle of next week. (See aerial photo taken 3/24 HERE).

March 23, 2023 – Sand disposal is complete!  Marinex crews are now pulling apart the dredge pipe and stacking it for removal from the beach.  Please be patient as they move west down South Beach. 

March 20, 2023 – Sand disposal is in front of Beach Access # 29 off Scotch Bonnet Lane. It looks like they have less than 1,000 linear feet left to complete. The project ends at Beach Access # 31 near Killegray Ridge.

March 16, 2023 – Sand disposal is located in front of Beach Access # 27 which is off Brown Pelican Trail.

March 10, 2023 – Sand disposal is located in front of Beach Access #25 which is off Peppervine Trail.

March 6, 2023 – Sand disposal is in front of Beach Access #21 which is off Silversides Trail.

February 27, 2023 – Sand disposal is just west of Beach Access #20 near Sandspur Trail.

February 20, 2023 – Sand disposal is just east of Beach Access #18 near Starrush Trail.

February 15, 2023 – Sand disposal is located right in front of Beach Access #18 which is off of Starrush Trail.

February 6, 2023 – Sand disposal is located east of Beach Access #17 near 332 S. Bald Head Wynd.

January 31, 2023 – Sand disposal is approaching Beach Access #17. The construction area now passes this access.

January 24, 2023 – Sand disposal is between Beach Access #15 and Beach Access #17, behind 320 S. Bald Head Wynd.

January 18, 2023 – Sand disposal is located at Beach Access #15.  Production has been impacted by inclement weather this week.  Dredging should resume on Friday 1/20/23. See aerial photo taken 1/15/23 HERE.

January 13, 2023 – Sand disposal has almost reached Beach Access #15. Operations were suspended today for weather and mechanical issues, as of this morning they were hoping to start back up later this afternoon.

January 11, 2023 – Sand disposal is currently located west of Beach Access #15, between 308 and 314 S. Bald Head Wynd.

January 10, 2023 – Several aerial photos of the project were taken over the weekend. View a slideshow of them HERE.

January 6, 2023 – Sand disposal is currently located just west of Beach Access #13 which is across from the Villas.

January 4, 2023 – The estimated project end date has been updated from March 10, 2023, to April 3, 2023.

December 21, 2022 – Marinex Construction is expected to suspend operations from December 22 through December 28, 2022, for the holiday.

December 7, 2022 – Marinex is expected to have a line to the island today and could start pumping sand on the beach as early as Friday, December 9, weather permitting.

December 1, 2022 – Village staff met with the Army Corps of Engineers and Marinex Construction staff for a pre-construction meeting. Marinex reported that construction (sand pumping) on the beach is expected to begin in 10 days, weather permitting.

November 30, 2022 – The Savannah Dredge arrived and is located next to Battery Island.


Frequently Asked Questions:

Q: Why isn’t the sand going in front of the Shoal’s Club when it is needed there the most?
A: Since this is an Army Corps of Engineers project solely funded by the federal government through Congressional appropriations, and the sand source per the Sand Management Plan (“SMP”) is the sand dredged from the federal navigation shipping channel to ensure the channel remains open, the Village does not have any direct authority over the project and where the sand will go. The Village can ask and did so last time the Corps did this project in 2021 and at that time the project budget funded by Congress and the quantity of sand dredged from the channel allowed for the sand to be placed from the west end of South Beach down near the Shoals Club.  For this Corps project, the funding appropriated and the volume of sand to be removed from the shipping channel was not enough to the extent that the Village considered expending Village funds to add additional material so it could get down in front of the Shoals Club as an additional contract to the Corps contract while the dredge was here, but decided against it at the recommendation of the Village’s coastal engineer primarily because the quality of sand did not justify the cost share the Village would have to pay.

At this point, the Village is working on the permitting to borrow sand from a new area of Jay Bird Shoals and is still pursuing a permit for sand from the adjacent Frying Pan Shoals.  A future privately funded Village beach nourishment project is planned for the winter of 2025 that will look to address the erosion at the east end of south beach and this topic will be discussed at the annual Council Retreat in February (7th  and 8th).  Our coastal engineer will be updating the Council on the status of the shoreline management program to include a discussion on details of the future Village beach nourishment project and erosion mitigation efforts specific to the area at the Shoals Club.

To date, the Village has worked in assisting the Shoals Club and its engineer with obtaining state permits through the Division of Coastal Management for the installation of temporary erosion control structures (i.e., “sand bags”) over the summer that have helped to protect the private infrastructure and minimize the ongoing erosion.