Past Project Information
Beach disposal or sand replacement activities on Bald Head Island since 1991.
Year | Volume | Sponsor | Location |
1991 | 0.35 ± Mcy | VBHI | (Sta. 24+00 to 138+00) |
1996 | 0.65 ± Mcy | VBHI | (Sta. 24+00 to 142+00) |
1997 | 0.45 ± Mcy | VBHI | (Sta. 24+00 to 128+00) |
2001 | 1.849 ± Mcy | USACE* | South Beach (Sta. 41 +60 to 205+50) |
2005 | 1.217 ± Mcy | USACE* | South Beach (Sta. 46+00 to 126+00) |
2006 | 47,800 cy | VBHI | West Beach (Sta. 16+00 to 34+00) |
2007 | 0.9785 ± Mcy | USACE* | South Beach (Sta. 46+00 to 174+00) |
2009/10 | 1.850 ± Mcy | VBHI | West Beach (Sta. 8+00 to 32+00) South Beach (Sta. 40+00 to 190+00) |
2012 | 137,990 cy | FEMA/VBHI | West Beach & Western South Beach |
2013 | 1.566 ± Mcy | USACE* | South Beach (Sta. 44+00 to 150+00) |
2013 | 92,500 cy | USACE* | West Beach (Sta. 8+00 to 27+00) |
2015 | 1.33 ± Mcy | USACE* | South Beach (Sta. 41 +50 to 154+00) |
2016/17 | 50,000 cy | VBHI | West Beach and Row Boat Row |
2018/19 | 1.1 Mcy | VBHI | South Beach (Sta. 49+00 to Sta. 146+00) |
2021 | 1.61 Mcy | USACE* | South Beach (Sta. 60+00 to Sta. 212+00) |
2023 | 1.3 Mcy | USACE* | South Beach (Sta. 60+00 to Sta. 165+00) |
* Disposal pursuant to the Wilmington Harbor Sand Management Plan (Appendix A).
VBHI = Village of Bald Head Island
USACE = US Army Corps of Engineers
FEMA = Federal Emergency Management Agency
Click HERE for aerial photos showing the location of the stations referenced above.
Erosion Control Structures (1994 to 2019)
Year | Location | Description |
1994 | Western South Beach | Sandbag revetment located along 645 feet of the back-beach berm. |
1996 (March) | Western South Beach | Sixteen (16) soft groins (geotextile tube-type structures) were constructed of geotextile material and sand fill. |
2003/2004 | Western South Beach | Rehabilitation of 1994 constructed sandbag revetment. Revetment lengthened by approximately 200 reel and base width increased to 40 ft and crest elevation raised to +12 ft-NGVD. |
2005 (January to March) | Western South Beach | Replacement of 1996 constructed sand tube groin field. Minor changes in groin location were made in an effort to improve performance. Similarly, experimental “tapered” tubes were deployed in an attempt to better accommodate beach profile recession over time. |
2009 | Western South Beach | Complete rehabilitation of the sand tube groin field. Some adjustment of groin lengths, and the westward relocation of groin no. 16 were made in an attempt to refine the project design. |
2011 | Western South Beach | 300 ft. sandbag revetment was constructed on the downdrift (western side) of the last sand tube groin in order to protect several endangered residential structures. |
2013 | Western South Beach | In the spring of 2013, the westernmost five (5) sand tube groins were replaced in their entirety. This work was co-funded by FEMA as part of a post-Irene damage mitigation effort. The project P. W. was BHGJS04 in accordance with FEMA declaration 4019 DR NC. |
2015 | Western South Beach | In the spring of 2015, construction was initiated on a single 1,300 ft. long rock terminal groin designed to complement future placement or beach fill at South Beach. At that time, the westernmost three (3) geotextile tube groins were removed in their entirety. A detailed description of the project is provided in Monitoring Report No. 15 (Olsen 2017). |
2015 | Bald Head Marina | The two marina entrance channel structures seaward of Row-Boot-Row originally constructed by Bald Head Island, Ltd., were modified through the addition of rock extensions. |
2017 | Row Boat Row | Two (2) detached breakwaters were constructed just north of the Marina Entrance. Construction details are provided in Monitoring Report No. 16 (Olsen. 2018). |
2019 | Western South Beach | All remaining 13 sand tube groins were removed and replaced. |