2025 CSDR Project

The Village of Bald Head Island has planned for a Coastal Storm Damage Reduction (CSDR) project that will begin in the fall of 2024 and will be completed in early 2025.

The Village contracted with Marinex Construction to dredge beach-quality sand from Jay Bird Shoals and place it on the west end of the terminal groin down through the groin tubes. The sand fill will restart east of Muscadine Wynd and fill to the east end of the Shoals Club (see map below).

With the dry sand beach nourishment in place at the west end of South Beach, the Village also plans to remove and replace all groin tubes in the soft-tube groin field.  McPherson Marine Services will perform this work.

As work progresses on this project, updates will be posted below and via our social media channels (HERE).

The photo above is from the 2022/2023 Wilmington Harbor Inner Ocean Bar Project. The method of sand placement seen in the photo will be used in the 2025 CSDR project.

DOCUMENTS

CAMA Permit Application with Project Details

How Beach Nourishment Works

Article: An Overview of BHI’s Shoreline Protection Program in Advance of the Village’s 2025 Project

Brochure: 2025 Coastal Storm Damage Reduction Project


CONTRACTOR:  Marinex Construction

DREDGE:  Savannah – Cutter suction dredge

Photo of Dredge Savannah staged next to Battery Island. Marinex will be staging equipment near this location during the project.

CONSTRUCTION START DATE:  First week in December (this is the approximate time that sand placement will begin and is subject to change).

APPROXIMATE END DATE:   April 30, 2025 (this date is subject to change)*

MATERIAL AMOUNT:  Approximately 1,000,000 cubic yards

*Start and end dates are rough estimates since weather and mechanical impacts can change the project schedule.

PLACEMENT:  Sand will be placed from the west end of the terminal groin down through the groin tubes, then the sand fill will restart east of Muscadine Wynd, and fill to the east end of the Shoals Club.

WHAT TO EXPECT:  The beach will remain open except for the areas of immediate construction where a 1,000-foot section of the beach will be closed at any given time when nourishment is underway. Due to the many variables associated with the construction progress, such as mechanical or weather impacts, it is extremely difficult to forecast when the contractor will close a particular section of the beach. There will be a large pipe that carries the sand slurry down the beach and heavy excavation equipment which will be working 24/7 until the project is completed. There will be noise from the large machinery 24/7, this will include the “backup signals” from the machines and lighting which are required for the safety of the crew. Sand ramps will be spaced along the beach (approximately every 400 feet) to allow beachgoers to walk over the pipe and access the ocean.

Please help the construction crew by being mindful of the construction fencing and signage. Do not go beyond any signage or barriers as doing so may place yourself and others in harm’s way.

INQUIRIES:  Can go to public.information@villagebhi.org or (910) 457-9700 ext. 1025

PROGRESS MAP:  The map below indicates where the beach fill will be placed (green shaded areas), where the soft-tube groins are located (blue lines), where the borrow area is located (black box in the water), and the numbered beach accesses (blue pins). Sand placement will begin on the west end of South Beach and move east. Equipment will be staged near Beach Access #11 (Sandpiper Trail). As the project proceeds, yellow pins will be added to the map to indicate where the beach fill is being placed. Click on the yellow pins for photos and/or descriptions. Once the beach fill moves past the soft-tube groins, the Village’s contractor will remove them and replace them with new ones. Any updates on this project phase will be marked with purple pins. Additional project updates will be posted below the map.

View on Google Maps


UPDATES:

December 18, 2024 (posted): Our dredging contractor has passed the oceanfront homes west of Beach Access #11 and sand placement is currently just to the east of the new pickleball courts at BHI Club.

December 12, 2024 (posted): Beach fill placement has started as of this evening.

November 27, 2024 (posted): Equipment mobilization has started. The equipment and pipe will be staged near Beach Access #11 (Sandpiper Trail).

November 14, 2024 (posted)Mobilization of pipe and equipment is expected to begin the week of 11/18/24. Beach fill placement is expected to start the first week of December 2024.

End of October/beginning of November – Pre-construction meetings & surveys conducted.